Drainage Improvements are anticipated to start Monday January 6, 2020 on Grand Oak Road adjacent to #38, and continue at various locations on Grand Oak Road, Pleasantwood Drive, and Dogwood Drive. Dig It Construction of Dennis, Mass. is the General Contractor. They have scheduled the work sequence in the following order: Site 4, 6, 1, 5, 2, 3 as shown on the attached overview map. Access to area homes at each respective location may be periodically delayed while the work is ongoing. Full access will be restored at the end of each work day. Work hours are 7am to 5pm, Monday - Friday. For more information, please contact the Engineering Department at 508-833-8000 or by email at engineering@sandwichmass.org.